Why it matters
Many factories do not have enough roof area to meet their load. Open access lets them source solar power at scale from a plant in the same state, often at a landed cost below the industrial grid tariff, and to raise their renewable share for ESG targets.
How it works in India
- Developer builds a solar plant (captive, group captive or third-party).
- Consumer signs a long-term PPA.
- Power is injected into the grid and adjusted against the consumer’s meter.
- State charges and surcharges apply.
| Cost element | Notes (indicative) |
|---|---|
| Solar generation tariff | Often ₹3–4/kWh |
| Wheeling + transmission + losses | Varies by state and voltage |
| Cross-subsidy surcharge | Exempt for captive under rules; varies |
Charges and procedures differ by state commission, and approvals go through the state nodal agency or the central green energy open access portal. Read our open access solar guide and C&I solar guide.
Related terms: DISCOM, time-of-day tariff. Explore commercial solar.
Frequently asked questions
Who can use green energy open access?
Under the Green Energy Open Access Rules 2022, consumers with a contract demand or sanctioned load of 100 kW or more can apply; captive users have no load limit.
What charges apply in open access?
Transmission and wheeling charges, cross-subsidy surcharge, additional surcharge (with relief for green power), banking charges and losses, as set by each state commission.