Net Metering in India: Complete 2026 Guide

How net metering works for rooftop solar in India, how it differs from gross and net billing, what varies by state, and how to apply step by step.

Quick answer: Net metering lets you export surplus rooftop solar power to your DISCOM and subtract it from the units you import, so you pay only for net consumption. A bi-directional meter records both flows. Capacity is usually capped at your sanctioned load, and surplus at year-end is paid at a lower regulated rate. Rules vary by state.

How does net metering work?

A rooftop solar system produces most of its power between about 9 am and 4 pm. If your home or business is using less than the panels produce, the surplus flows into the grid. At night, or when solar output is low, you draw power from the grid. A bi-directional (net) meter records both export and import. At the end of each billing cycle, the DISCOM bills you only for the difference.

Example: in a month, your 3 kW system exports 200 units and you import 280 units. You are billed for 80 units, plus fixed charges. If export exceeds import, the surplus is carried forward as credit to the next bill, usually until the end of the settlement period.

What is the difference between net metering, net billing and gross metering?

Mechanism How it works Value of exported unit Typical use
Net metering Exports offset imports unit for unit Equal to your retail tariff (within the period) Residential, many small C&I
Net billing / net feed-in Imports billed at retail tariff; exports credited at a separate, lower rate Lower than retail tariff C&I in some states
Gross metering All generation exported and paid at a feed-in tariff; all consumption billed separately Fixed feed-in tariff Some RESCO and larger systems

For most households, net metering offers the best value because every exported unit offsets a unit that would otherwise cost the full slab tariff.

What are the national rules?

The Electricity (Rights of Consumers) Rules, 2020, as amended, set the framework: prosumers can install rooftop solar up to their sanctioned load (or up to a limit set by the state commission), with net metering generally available up to 500 kW, and gross or net billing beyond that. Amendments have aimed to make approvals faster, including deemed approval for small systems (up to 10 kW) if the DISCOM does not respond within the prescribed time, and waiving technical feasibility studies for small systems. However, each State Electricity Regulatory Commission (SERC) issues its own regulations, so the details differ.

How do net metering rules vary by state?

The notes below are indicative summaries to help you ask the right questions. Regulations change frequently, so always confirm with your DISCOM or the SERC’s latest order.

State Indicative notes (verify before applying)
Maharashtra Net metering for residential consumers; MERC regulations introduced different treatment for larger C&I systems, and time-of-day settlement for some categories. MSEDCL handles applications online.
Gujarat Strong residential uptake; residential consumers can install above sanctioned load in some cases. C&I treatment has changed over time, with banking charges for certain categories.
Rajasthan Net metering for residential and small consumers; excellent solar irradiation of around 5–5.5 units per kW per day in many districts.
Uttar Pradesh Net metering for residential consumers; state top-up subsidy has been offered alongside PM Surya Ghar at times.
Delhi Net metering with a solar policy that has offered generation-based incentives for residential and RWA systems at times; DISCOMs (BSES, Tata Power-DDL) process online.
Tamil Nadu Net feed-in for many categories; network or grid support charges have applied to some C&I categories.
Karnataka Net metering for residential consumers via BESCOM and other ESCOMs; separate tariff orders for gross metering.
Telangana Net metering for residential consumers; limits linked to sanctioned load and transformer capacity.

Across states, watch for: capacity limits relative to sanctioned load, distribution transformer limits (often 30–75% of transformer capacity), the settlement period (monthly, half-yearly or annual), the rate paid for surplus, and any banking or grid support charges for C&I.

What documents are needed for net metering?

  • Latest electricity bill and consumer number
  • Identity proof (Aadhaar) and ownership proof of the premises
  • Application form (online on the DISCOM or PM Surya Ghar portal)
  • System details: capacity, module and inverter make, model and serial numbers
  • Inverter test certificates (IEC/BIS) and module datasheets
  • Single-line diagram and earthing details (often prepared by the installer)
  • Work completion report and installer’s certificate
  • Agreement with the DISCOM (net metering connection agreement)
  • For C&I: electrical inspectorate approval, board resolution and CEIG certificate where applicable

What is the step-by-step net metering process?

  1. Apply online with the DISCOM (for households, through pmsuryaghar.gov.in, which links to the DISCOM).
  2. Technical feasibility: the DISCOM checks transformer and feeder capacity. Small systems may get deemed approval.
  3. Install the system with an approved installer.
  4. Submit the work completion report and documents.
  5. Meter testing and installation: the DISCOM tests and installs the bi-directional meter (and sometimes a solar generation meter).
  6. Inspection and synchronisation: the DISCOM inspects the system and commissions it.
  7. Agreement and billing: sign the net metering agreement; your bills now show import, export and net units.

SolarEMS handles these steps for our customers. See our residential and commercial and industrial pages.

How should I size my system for net metering?

Because surplus at the end of the settlement period is usually paid at a lower rate, the best financial return comes from sizing your system to roughly match your annual consumption, not to maximise exports. Rough rule: annual units ÷ 1,300 gives the kW required in most of India. A household using 4,000 units a year would need about 3 kW. Calculate with our rooftop solar calculator and check payback with the ROI calculator.

How do I read a net metered bill?

  • Import (kWh): units drawn from the grid
  • Export (kWh): units sent to the grid
  • Net units: import minus export (plus any carried-forward credit)
  • Banked units: credit carried forward to the next cycle
  • Fixed/demand charges: still payable even if net units are zero

Compare your solar generation from the inverter or EMS app with exported units to understand how much solar you consume directly.

What are common net metering problems?

  • Delays in meter installation: follow up through the portal or DISCOM grievance cell.
  • Incorrect billing: sometimes export is billed as import after meter changes; check the first few bills carefully.
  • Transformer capacity limits: in dense areas, applications may be restricted; ask your installer to check early.
  • Load mismatch: if your sanctioned load is lower than your planned system, apply for load enhancement first.
  • Inverter tripping on high voltage: common on weak rural feeders; inverter settings may need DISCOM-approved adjustment.
Key takeaways

  • Net metering offsets imported units with exported solar units.
  • Capacity is usually limited to sanctioned load; rules vary by state.
  • Year-end surplus is often paid at a lower regulated rate, so size to consumption.
  • Small systems may get deemed approval under the national consumer rules.
  • Check your SERC and DISCOM regulations before applying.

Want us to handle net metering for you?

From the application to the meter installation and first bill check, our team manages the paperwork. Get a free solar quote.

Frequently asked questions

What is net metering?

Net metering lets a rooftop solar owner export surplus power to the grid and offset it against power imported later. A bi-directional meter records both, and you pay only for the net units consumed.

What happens to surplus units at the end of the year?

It depends on your state. Many DISCOMs settle annually, paying for surplus units at a regulated rate (often the average power purchase cost), which is lower than the retail tariff. Some states lapse or carry forward credits.

Is there a limit on solar capacity under net metering?

Most states cap capacity at the sanctioned load or contract demand, and some set an upper limit (often 500 kW or 1 MW) and feeder or transformer limits. Check your state regulations.

How long does net metering take?

For residential systems, typically 2–6 weeks after installation, depending on the DISCOM's inspection and meter availability.

Do commercial consumers get net metering?

In many states yes, within capacity limits, though some states apply gross metering or net billing for C&I consumers above certain sizes. Rules have changed frequently, so check current state regulations.